SEVENEN FRAMEWORK PROGRAMME

Design of thin-film nanocatalysts for on-chip fuel cell technology

Timeline

Timeline

 

Deliverable D2.1 : Reaction on conventional FC catalysts

Fulfilled and reported in month no. 18 of the project, on schedule..

Deliverable D5.2 : Pt-ceria catalysts

Fulfilled and reported in month no. 18 of the project, on schedule.

Deliverable D3.2 : Spectroelectrochemical cell system

Fulfilled and reported in month no. 18 of the project, on schedule.

Deliverable D3.1 : Conventional low PGM model catalysts

Fulfilled and reported in month no. 18 of the project, on schedule.

Milestone MS2 :     FC tests on Pt NCF

Fulfilled in month no. 12 of the project as a compound result of MS1, D4.1, D4.2, D5.1, D6.1 and D6.2.

Deliverable D6.2 :  Pre-evaluation of Pt NCF

Fulfilled and reported in month no. 12 of the project, on schedule.

Deliverable D5.1 : Reference Pt and Pt-Ru catalysts

Fulfilled and reported in month no. 12 of the project, on schedule. Only Pt catalysts researched.

Deliverable D7.2 :  Fabrication route of micro-FC

Draft report, the full report due in month no. 24 of the project.

Deliverable D7.1 :  Device architecture

Not delivered, when due in month no. 12. Finite elements modelling postponed, focus shifted to D7.2 and practival solution of the HW issues of micro FCs. New date of D7.1 delivery to be determined - tentatively, month no. 30.

Milestone MS1 :     Reference Pt NCF

Fulfilled in month no. 10 of the project as a compound result of D4.1, D4.2, D6.1 and partial results of D6.2 due later.

Deliverable D4.2 :  Nanoporous catalyst film growth

Fulfilled and reported in month no. 9 of the project, on schedule.

Deliverable D4.1 :  Porous membrane

Fulfilled and reported in month no. 9 of the project, on schedule.

Deliverable D8.1 :  Web site

Fulfilled by launching this www.chipcat.eu website in month no. 9 of the project.

Deliverable D6.1 :  Benchmark MEA

Fulfilled in month no. 6 of the project on schedule, as presented at the 2013 Management Committee meeting in Trieste.

Deliverable D1.1 :  Project office apointment

Fulfilled in month no. 2 of the project at the project's kick-off General Assembly meeting in Prague.